<thead id="nvvjx"><var id="nvvjx"><output id="nvvjx"></output></var></thead>

<sub id="nvvjx"><var id="nvvjx"></var></sub>
<address id="nvvjx"><listing id="nvvjx"><ins id="nvvjx"></ins></listing></address>

      <address id="nvvjx"><var id="nvvjx"></var></address><address id="nvvjx"><var id="nvvjx"></var></address>
      <sub id="nvvjx"><listing id="nvvjx"></listing></sub>

      <sub id="nvvjx"><dfn id="nvvjx"><ins id="nvvjx"></ins></dfn></sub>

      <address id="nvvjx"></address>

      <sub id="nvvjx"></sub>
      <sub id="nvvjx"><var id="nvvjx"><output id="nvvjx"></output></var></sub>
      <address id="nvvjx"><dfn id="nvvjx"></dfn></address>

      <address id="nvvjx"></address>

        <address id="nvvjx"><var id="nvvjx"><ins id="nvvjx"></ins></var></address>
          <thead id="nvvjx"><var id="nvvjx"><output id="nvvjx"></output></var></thead>
            當前位置:首頁
            > 資訊中心 > 媒體聚焦


            中國起重機械網:水電三局承建白河水電站安裝場首榀預制梁吊裝順利吊裝到位!


            發布日期:2018-11-26 字號:[ ] 分享

            日前,水電三局第一分局承建的白河水電站安裝場首榀預制梁吊裝順利吊裝到位,為后續施工奠定了基礎。

            本次吊裝的是安裝場預制梁,為確保預制梁吊裝施工順利進行,項目部成立了預制梁安裝小組,制定了嚴密的技術措施和安全保證措施,在項目部的精心組織和各部門通力配合下,經過緊張吊裝和精細調整,預制梁有條不紊地通過各道吊運工序,穩穩地被架橋機放進了兩個梁座間。

            白河水電站安裝場壩段寬41.5米,上下游總長75.2米,分兩個泄洪表孔,孔凈寬13.5米,孔凈高30.97米。頂板采用預制倒T梁+現澆結構。預制梁底寬1米,梁高1.3米,梁長為14.5米。根據設計圖紙,本次吊裝預制梁共計110根,單根預制梁混凝土7.68方,鋼筋重量3.3噸,單根預制梁總重約22噸。

            為保證本次項目的順利實施,在面臨施工前期圖紙供應不即時、現場施工人員調配不足、施工進度滯后等困難,項目部積極進行多方協調,及時調整施工隊伍進行趕搶,管理協調陣線前移,并積極組織現場人員、設備資源進行適當傾斜,確保產品質量滿足設計要求,確保了閘墩施工進度與年度計劃目標保持一致。

            現階段關鍵線路由閘墩混凝土澆筑轉變為壩頂預制梁施工,而此次安裝場首榀預制梁吊裝成功,為后續預制梁架設提供了經驗,也為安裝場年度計劃排架柱封頂奠定了基礎。